Concrete Girders Of An On-going Bridge Construction In Samar Fell & Break; Work Continues

Work goes on at the Gandara Parallel Bridge Project a day after two (2) concrete girders fell and break on the ground below the bridge.

Two (2) concrete girders fell and broke on the ground in the morning of November 17, 2026.  The incident was caused by lapses in the operation of the crane that caused one girder to swing hitting the other and caused both girders (1&2) to fall and break on the ground - about 6 meters more or less down from where both girders were launched.

The subject concrete girders measure 1.60m in depth, 0.771m bottom width and 35.00m in length.

Reliable information tells that Girders 1 & 2 were already launched (on November 16) a day before the incident.  In the morning of the day of the incident (November 17), launching of Girders 3 & 4 was in progress.  By procedures, however, there was the need to first remove the rollers under Girders 1 & 2 to put both in place on the bridge seat.  In the process of removing the rollers the incident happened.

The incident and the noise it created in social media – mostly malinformation, misinformation - about the incident - caused the Department of Public Works and Highways (DPWH) Secretary Banoy Lopez to issue official statement. A technical team was ordered to assess and ensure appropriate correction measures.

The statement also included a directive from President Ferdinand Marcos to immediately respond and ensure the safety of workers.

Confirming the information provided by the Contractor on the night of the incident, DPWH’s statement also assured that the incident did not cause injuries to any person and that the Contractor is taking responsibility for the incident thereby assuring that the damages to the girders will be at no cost to the government.

Starting November 18 (a day after the incident), the contractor continued works on the bridge by launching concrete girders available in the project site – working overtime even until the night.

On-going works until night time at the Gandara Parallel Bridge Project (November 19, 2026)
On-going works until night time at the Gandara Parallel Bridge Project (November 19, 2026)

Sources say that opinions and comments about “structural defects” and “use of substandard materials” are merely allegations and are without proof.

All girders used and to be used for the bridge were submitted for evaluation and have passed the required bridge load test.

CONTRACT AMOUNT:   The on-going works on the Gandara Parallel Bridge is under a bid amount of P92,562,061.50 with allocations made available in 2024. This data is written on the project billboard in the vicinity of the project site.

This is the second phase of the bridge project.  The first phase was earlier completed by the same contractor and is without any issue up to this time.

Sources vehemently deny about reports by local sources (media & vloggers) and national news outfits on television.

PROJECT INSPECTION:  A team from the DPWH, led by the Department Secretary is due on Friday, November 20, 2026.(CJ/JMM)

-Calbayog Journal, November 19, 2026